Sawmill hydrostation redevelopment. First annual report
Progress during the period from July 1979 to July 1980 in the redevelopment of the Sawmill Dam in New Hampshire as a run-of-river hydroelectric generating station is reported. This project should demonstrate the technical and economic feasibility of retrofitting existing dams for low-head hydro powe...
Format: | Report |
---|---|
Language: | English |
Published: |
Brown Co., Berlin, NH (USA). Engineering Dept.
1980
|
Subjects: | |
Online Access: | https://doi.org/10.2172/6890885 https://digital.library.unt.edu/ark:/67531/metadc1190702/ |
Summary: | Progress during the period from July 1979 to July 1980 in the redevelopment of the Sawmill Dam in New Hampshire as a run-of-river hydroelectric generating station is reported. This project should demonstrate the technical and economic feasibility of retrofitting existing dams for low-head hydro power plants. The topics discussed include licensing and permits, project planning, environmental concerns, engineering and design, safety, materials and equipment procurement, publicity, and construction status. (LCL) |
---|