Integrated dry NO sub x /SO sub 2 emissions control system
The DSI system design is approximately eighty percent completed. About eighty percent of the materials have been purchased for erection and setup of the DSI system. Most of the equipment and supply purchases have been made for the DCS. The Unit 4 outage started March 20, 1992 for the installation of...
Other Authors: | |
---|---|
Format: | Report |
Language: | English |
Published: |
Public Service Co. of Colorado, Denver, CO (United States)
1992
|
Subjects: | |
Online Access: | https://doi.org/10.2172/7282016 https://digital.library.unt.edu/ark:/67531/metadc1451118/ |
_version_ | 1821489677484425216 |
---|---|
author2 | United States. Department of Energy. |
collection | University of North Texas: UNT Digital Library |
description | The DSI system design is approximately eighty percent completed. About eighty percent of the materials have been purchased for erection and setup of the DSI system. Most of the equipment and supply purchases have been made for the DCS. The Unit 4 outage started March 20, 1992 for the installation of the remaining project equipment. overall field construction activities continued on the flyash, boiler, dry sorbent injection and humidification systems. Noell performed startup and testing activities for the urea injection system. FERCO completed baseline urea injection tests March 6, 1992. Preliminary analyses were reviewed at a project review meeting on March 11, 1992. The HVAC platform and duct work for the DCS was installed. B W mobilized on site. Demolition and construction activities began to support the future installation of the low NO, burners and ports. CSM completed the batch reactor vessel. The sorbent and flyash silos were erected for the DSI system. The humidification building was erected and piping for the fly ash silo started. |
format | Report |
genre | Carbonic acid |
genre_facet | Carbonic acid |
id | ftunivnotexas:info:ark/67531/metadc1451118 |
institution | Open Polar |
language | English |
op_collection_id | ftunivnotexas |
op_doi | https://doi.org/10.2172/7282016 |
op_relation | other: DE92019717 rep-no: DOE/PC/90550-T6 grantno: FC22-91PC90550 doi:10.2172/7282016 osti: 7282016 https://digital.library.unt.edu/ark:/67531/metadc1451118/ ark: ark:/67531/metadc1451118 |
publishDate | 1992 |
publisher | Public Service Co. of Colorado, Denver, CO (United States) |
record_format | openpolar |
spelling | ftunivnotexas:info:ark/67531/metadc1451118 2025-01-16T21:28:13+00:00 Integrated dry NO sub x /SO sub 2 emissions control system United States. Department of Energy. 1992-05-15 13 pages Text https://doi.org/10.2172/7282016 https://digital.library.unt.edu/ark:/67531/metadc1451118/ English eng Public Service Co. of Colorado, Denver, CO (United States) other: DE92019717 rep-no: DOE/PC/90550-T6 grantno: FC22-91PC90550 doi:10.2172/7282016 osti: 7282016 https://digital.library.unt.edu/ark:/67531/metadc1451118/ ark: ark:/67531/metadc1451118 Urea Chemical Reactions Wastes 200202* -- Fossil-Fueled Power Plants-- Waste Management-- Noxious Gas & Particulate Emissions Desulfurization Organic Compounds Progress Report Document Types Amides Air Pollution Control Power Plants Gaseous Wastes Flue Gas 20 Fossil-Fueled Power Plants Sorbent Injection Processes Burners Combined Soxnox Processes Control Carbonic Acid Derivatives Organic Nitrogen Compounds Denitrification Fossil-Fuel Power Plants Thermal Power Plants Pollution Control Report 1992 ftunivnotexas https://doi.org/10.2172/7282016 2019-05-04T22:09:03Z The DSI system design is approximately eighty percent completed. About eighty percent of the materials have been purchased for erection and setup of the DSI system. Most of the equipment and supply purchases have been made for the DCS. The Unit 4 outage started March 20, 1992 for the installation of the remaining project equipment. overall field construction activities continued on the flyash, boiler, dry sorbent injection and humidification systems. Noell performed startup and testing activities for the urea injection system. FERCO completed baseline urea injection tests March 6, 1992. Preliminary analyses were reviewed at a project review meeting on March 11, 1992. The HVAC platform and duct work for the DCS was installed. B W mobilized on site. Demolition and construction activities began to support the future installation of the low NO, burners and ports. CSM completed the batch reactor vessel. The sorbent and flyash silos were erected for the DSI system. The humidification building was erected and piping for the fly ash silo started. Report Carbonic acid University of North Texas: UNT Digital Library |
spellingShingle | Urea Chemical Reactions Wastes 200202* -- Fossil-Fueled Power Plants-- Waste Management-- Noxious Gas & Particulate Emissions Desulfurization Organic Compounds Progress Report Document Types Amides Air Pollution Control Power Plants Gaseous Wastes Flue Gas 20 Fossil-Fueled Power Plants Sorbent Injection Processes Burners Combined Soxnox Processes Control Carbonic Acid Derivatives Organic Nitrogen Compounds Denitrification Fossil-Fuel Power Plants Thermal Power Plants Pollution Control Integrated dry NO sub x /SO sub 2 emissions control system |
title | Integrated dry NO sub x /SO sub 2 emissions control system |
title_full | Integrated dry NO sub x /SO sub 2 emissions control system |
title_fullStr | Integrated dry NO sub x /SO sub 2 emissions control system |
title_full_unstemmed | Integrated dry NO sub x /SO sub 2 emissions control system |
title_short | Integrated dry NO sub x /SO sub 2 emissions control system |
title_sort | integrated dry no sub x /so sub 2 emissions control system |
topic | Urea Chemical Reactions Wastes 200202* -- Fossil-Fueled Power Plants-- Waste Management-- Noxious Gas & Particulate Emissions Desulfurization Organic Compounds Progress Report Document Types Amides Air Pollution Control Power Plants Gaseous Wastes Flue Gas 20 Fossil-Fueled Power Plants Sorbent Injection Processes Burners Combined Soxnox Processes Control Carbonic Acid Derivatives Organic Nitrogen Compounds Denitrification Fossil-Fuel Power Plants Thermal Power Plants Pollution Control |
topic_facet | Urea Chemical Reactions Wastes 200202* -- Fossil-Fueled Power Plants-- Waste Management-- Noxious Gas & Particulate Emissions Desulfurization Organic Compounds Progress Report Document Types Amides Air Pollution Control Power Plants Gaseous Wastes Flue Gas 20 Fossil-Fueled Power Plants Sorbent Injection Processes Burners Combined Soxnox Processes Control Carbonic Acid Derivatives Organic Nitrogen Compounds Denitrification Fossil-Fuel Power Plants Thermal Power Plants Pollution Control |
url | https://doi.org/10.2172/7282016 https://digital.library.unt.edu/ark:/67531/metadc1451118/ |