Qinghai-Tibet Railway, China and the Solutions to Its Major Geotechnical Problems for Construction

The Qinghai-Tibet Railway (QTR) is the highest-elevation one for passenger trains in the world and the first railway to connect central China to Tibet. Construction of this railway starting in 2001 had to contend with major geotechnical challenges, such as permafrost, environmental protection and se...

Full description

Bibliographic Details
Main Authors: Wang, Lanmin, Wu, Zhijian, Sun, Junjie, Zhang, Luxin
Format: Text
Language:unknown
Published: Scholars' Mine 2008
Subjects:
Online Access:https://scholarsmine.mst.edu/icchge/6icchge/session13/9
https://scholarsmine.mst.edu/cgi/viewcontent.cgi?article=2970&context=icchge
id ftmissouriunivst:oai:scholarsmine.mst.edu:icchge-2970
record_format openpolar
spelling ftmissouriunivst:oai:scholarsmine.mst.edu:icchge-2970 2023-05-15T17:57:01+02:00 Qinghai-Tibet Railway, China and the Solutions to Its Major Geotechnical Problems for Construction Wang, Lanmin Wu, Zhijian Sun, Junjie Zhang, Luxin 2008-08-11T07:00:00Z application/pdf https://scholarsmine.mst.edu/icchge/6icchge/session13/9 https://scholarsmine.mst.edu/cgi/viewcontent.cgi?article=2970&context=icchge unknown Scholars' Mine https://scholarsmine.mst.edu/icchge/6icchge/session13/9 https://scholarsmine.mst.edu/cgi/viewcontent.cgi?article=2970&context=icchge © 2008 Missouri University of Science and Technology, All rights reserved. http://creativecommons.org/licenses/by-nc-nd/4.0/ CC-BY-NC-ND International Conference on Case Histories in Geotechnical Engineering Geotechnical Engineering text 2008 ftmissouriunivst 2022-08-09T20:44:38Z The Qinghai-Tibet Railway (QTR) is the highest-elevation one for passenger trains in the world and the first railway to connect central China to Tibet. Construction of this railway starting in 2001 had to contend with major geotechnical challenges, such as permafrost, environmental protection and seismic hazards. Its completion in 2006 is a remarkable feat in the world’s railway construction history and crystallization of wisdom of human beings. In this paper, the planning and preparing history and the construction project of QTR are introduced. The major three thorny problems, permafrost, lack of oxygen and environmental frangibility for the construction and their solutions are presented, which are active methods of riprap roadbeds, heat pipe roadbed and bridges over land for permafrost, health care system for lack of oxygen and environmental protection measures for construction and operation. Seismic safety assessment was carried out for earthquake damage mitigation of the railway. The laboratory test, field test and observation, and it’s operation have shown that design, construction, and measures for earthquake hazards mitigation and environmental protection of the Qinghai-Tibet Railway are completely successful. Text permafrost Missouri University of Science and Technology (Missouri S&T): Scholars' Mine
institution Open Polar
collection Missouri University of Science and Technology (Missouri S&T): Scholars' Mine
op_collection_id ftmissouriunivst
language unknown
topic Geotechnical Engineering
spellingShingle Geotechnical Engineering
Wang, Lanmin
Wu, Zhijian
Sun, Junjie
Zhang, Luxin
Qinghai-Tibet Railway, China and the Solutions to Its Major Geotechnical Problems for Construction
topic_facet Geotechnical Engineering
description The Qinghai-Tibet Railway (QTR) is the highest-elevation one for passenger trains in the world and the first railway to connect central China to Tibet. Construction of this railway starting in 2001 had to contend with major geotechnical challenges, such as permafrost, environmental protection and seismic hazards. Its completion in 2006 is a remarkable feat in the world’s railway construction history and crystallization of wisdom of human beings. In this paper, the planning and preparing history and the construction project of QTR are introduced. The major three thorny problems, permafrost, lack of oxygen and environmental frangibility for the construction and their solutions are presented, which are active methods of riprap roadbeds, heat pipe roadbed and bridges over land for permafrost, health care system for lack of oxygen and environmental protection measures for construction and operation. Seismic safety assessment was carried out for earthquake damage mitigation of the railway. The laboratory test, field test and observation, and it’s operation have shown that design, construction, and measures for earthquake hazards mitigation and environmental protection of the Qinghai-Tibet Railway are completely successful.
format Text
author Wang, Lanmin
Wu, Zhijian
Sun, Junjie
Zhang, Luxin
author_facet Wang, Lanmin
Wu, Zhijian
Sun, Junjie
Zhang, Luxin
author_sort Wang, Lanmin
title Qinghai-Tibet Railway, China and the Solutions to Its Major Geotechnical Problems for Construction
title_short Qinghai-Tibet Railway, China and the Solutions to Its Major Geotechnical Problems for Construction
title_full Qinghai-Tibet Railway, China and the Solutions to Its Major Geotechnical Problems for Construction
title_fullStr Qinghai-Tibet Railway, China and the Solutions to Its Major Geotechnical Problems for Construction
title_full_unstemmed Qinghai-Tibet Railway, China and the Solutions to Its Major Geotechnical Problems for Construction
title_sort qinghai-tibet railway, china and the solutions to its major geotechnical problems for construction
publisher Scholars' Mine
publishDate 2008
url https://scholarsmine.mst.edu/icchge/6icchge/session13/9
https://scholarsmine.mst.edu/cgi/viewcontent.cgi?article=2970&context=icchge
genre permafrost
genre_facet permafrost
op_source International Conference on Case Histories in Geotechnical Engineering
op_relation https://scholarsmine.mst.edu/icchge/6icchge/session13/9
https://scholarsmine.mst.edu/cgi/viewcontent.cgi?article=2970&context=icchge
op_rights © 2008 Missouri University of Science and Technology, All rights reserved.
http://creativecommons.org/licenses/by-nc-nd/4.0/
op_rightsnorm CC-BY-NC-ND
_version_ 1766165363493437440