Ställtidsreducering med SMED-metoden vid Duroc Special Steel

Duroc Special Steel is a so called re-roller operation and is located within SSAB:s industrial area in Luleå. The production includes rolling, annealing and slitting of warm and cold rolled metal strips in customized sizes. Along with 17 other companies Duroc Special Steel represents the Duroc group...

Full description

Bibliographic Details
Main Author: Bergquist, Mattias
Format: Bachelor Thesis
Language:Swedish
Published: 2011
Subjects:
Online Access:http://urn.kb.se/resolve?urn=urn:nbn:se:ltu:diva-55688
id ftluleatu:oai:DiVA.org:ltu-55688
record_format openpolar
spelling ftluleatu:oai:DiVA.org:ltu-55688 2023-05-15T17:09:17+02:00 Ställtidsreducering med SMED-metoden vid Duroc Special Steel Bergquist, Mattias 2011 application/pdf http://urn.kb.se/resolve?urn=urn:nbn:se:ltu:diva-55688 swe swe http://urn.kb.se/resolve?urn=urn:nbn:se:ltu:diva-55688 Local c86e034b-4444-4b80-9a34-8c4e55f44077 info:eu-repo/semantics/openAccess Technology Teknik SMED ställtid omställningsarbete participation flaskhals Student thesis info:eu-repo/semantics/bachelorThesis text 2011 ftluleatu 2022-10-25T20:52:57Z Duroc Special Steel is a so called re-roller operation and is located within SSAB:s industrial area in Luleå. The production includes rolling, annealing and slitting of warm and cold rolled metal strips in customized sizes. Along with 17 other companies Duroc Special Steel represents the Duroc group. The company has recently found that the slitting lines set up time is far too long considering the current state of production. In some cases the slitting line becomes a bottleneck operation. This occurs when the employees do not have enough time to finish a set up before the new product is ready to be produced. Therefore a study is needed to examine what can be done to shorten the set up time and also improve the building operation of the slitting tools, which is the main part of the set work. As a result, this thesis has been developed based on these two main problems; set up time and building slitting tools. The goal of this master thesis is therefore to demonstrate the ability to shorten set up times, improve set work and its work practices and also give solutions as to how this can be accomplished. The project’s primary implementation is based on a literature study consisting mainly of the SMED method, but also set up time and workers participation. Additionally during the project SMED has been the prinicipal tool for the task at hand and has therefore had a significant role in the work. Workers participation, in the form of completed workshops, has also been of great importance to the project. The literature study was used to anchor the implementation of the project and its ideas to achieve a result with credibility. A specification of demands was made containing criteria of what the solutions would bring and result in. It was later used in the project’s final stage to evaluate the different solutions and ideas. The problem solving of this master thesis has resulted in several proposals of what can be done to shorten the set up time, reduce the risk of bottleneck operations, improve set work and the building ... Bachelor Thesis Luleå Luleå Luleå Luleå University of Technology Publications (DiVA)
institution Open Polar
collection Luleå University of Technology Publications (DiVA)
op_collection_id ftluleatu
language Swedish
topic Technology
Teknik
SMED
ställtid
omställningsarbete
participation
flaskhals
spellingShingle Technology
Teknik
SMED
ställtid
omställningsarbete
participation
flaskhals
Bergquist, Mattias
Ställtidsreducering med SMED-metoden vid Duroc Special Steel
topic_facet Technology
Teknik
SMED
ställtid
omställningsarbete
participation
flaskhals
description Duroc Special Steel is a so called re-roller operation and is located within SSAB:s industrial area in Luleå. The production includes rolling, annealing and slitting of warm and cold rolled metal strips in customized sizes. Along with 17 other companies Duroc Special Steel represents the Duroc group. The company has recently found that the slitting lines set up time is far too long considering the current state of production. In some cases the slitting line becomes a bottleneck operation. This occurs when the employees do not have enough time to finish a set up before the new product is ready to be produced. Therefore a study is needed to examine what can be done to shorten the set up time and also improve the building operation of the slitting tools, which is the main part of the set work. As a result, this thesis has been developed based on these two main problems; set up time and building slitting tools. The goal of this master thesis is therefore to demonstrate the ability to shorten set up times, improve set work and its work practices and also give solutions as to how this can be accomplished. The project’s primary implementation is based on a literature study consisting mainly of the SMED method, but also set up time and workers participation. Additionally during the project SMED has been the prinicipal tool for the task at hand and has therefore had a significant role in the work. Workers participation, in the form of completed workshops, has also been of great importance to the project. The literature study was used to anchor the implementation of the project and its ideas to achieve a result with credibility. A specification of demands was made containing criteria of what the solutions would bring and result in. It was later used in the project’s final stage to evaluate the different solutions and ideas. The problem solving of this master thesis has resulted in several proposals of what can be done to shorten the set up time, reduce the risk of bottleneck operations, improve set work and the building ...
format Bachelor Thesis
author Bergquist, Mattias
author_facet Bergquist, Mattias
author_sort Bergquist, Mattias
title Ställtidsreducering med SMED-metoden vid Duroc Special Steel
title_short Ställtidsreducering med SMED-metoden vid Duroc Special Steel
title_full Ställtidsreducering med SMED-metoden vid Duroc Special Steel
title_fullStr Ställtidsreducering med SMED-metoden vid Duroc Special Steel
title_full_unstemmed Ställtidsreducering med SMED-metoden vid Duroc Special Steel
title_sort ställtidsreducering med smed-metoden vid duroc special steel
publishDate 2011
url http://urn.kb.se/resolve?urn=urn:nbn:se:ltu:diva-55688
genre Luleå
Luleå
Luleå
genre_facet Luleå
Luleå
Luleå
op_relation http://urn.kb.se/resolve?urn=urn:nbn:se:ltu:diva-55688
Local c86e034b-4444-4b80-9a34-8c4e55f44077
op_rights info:eu-repo/semantics/openAccess
_version_ 1766065321625518080