Analisis Alternatif Percepatan Projek Reparasi ORCA LAUT 7296 Mengguankan Metode Korelasi SPSS

Repair activities are one of the ship maintenance schedules. In the ORCA LAUT 7296 ship repair project, acceleration of project activities is carried out to save repair time. This is done so that the ship can operate immediately and the shipyard can receive a new ship project that you want to repair...

Full description

Bibliographic Details
Main Authors: Anauta Lungiding A.R, Nely Handayani Kusuma Hadi
Format: Article in Journal/Newspaper
Language:English
Published: Pusat Riset dan Inovasi Nasional 2023
Subjects:
Online Access:https://ejurnal.politeknikpratama.ac.id/index.php/jupiman/article/view/1567
https://doi.org/10.55606/jupiman.v2i2.1567
id ftlppmpolprapurw:oai:ojs2.ejurnal.politeknikpratama.ac.id:article/1567
record_format openpolar
spelling ftlppmpolprapurw:oai:ojs2.ejurnal.politeknikpratama.ac.id:article/1567 2024-06-16T07:42:32+00:00 Analisis Alternatif Percepatan Projek Reparasi ORCA LAUT 7296 Mengguankan Metode Korelasi SPSS Anauta Lungiding A.R Nely Handayani Kusuma Hadi 2023-04-28 application/pdf https://ejurnal.politeknikpratama.ac.id/index.php/jupiman/article/view/1567 https://doi.org/10.55606/jupiman.v2i2.1567 eng eng Pusat Riset dan Inovasi Nasional https://ejurnal.politeknikpratama.ac.id/index.php/jupiman/article/view/1567/1553 https://ejurnal.politeknikpratama.ac.id/index.php/jupiman/article/view/1567 doi:10.55606/jupiman.v2i2.1567 Copyright (c) 2023 Jurnal Publikasi Ilmu Manajemen Jurnal Publikasi Ilmu Manajemen; Vol. 2 No. 2 (2023): Juni : Jurnal Publikasi Ilmu Manajemen; 01-15 2963-766X 2963-8712 10.55606/jupiman.v2i2 Alternative Acceleration Repair Correlation SPSS info:eu-repo/semantics/article info:eu-repo/semantics/publishedVersion Peer-reviewed Article 2023 ftlppmpolprapurw https://doi.org/10.55606/jupiman.v2i2.156710.55606/jupiman.v2i2 2024-05-22T23:46:22Z Repair activities are one of the ship maintenance schedules. In the ORCA LAUT 7296 ship repair project, acceleration of project activities is carried out to save repair time. This is done so that the ship can operate immediately and the shipyard can receive a new ship project that you want to repair or build a new ship. ORCA LAUT 7296 has several jobs, especially on hull replating activities due to the ship having run aground and experiencing a leak. In this study, an analysis of project acceleration was carried out using the correlation method with the help of the SPSS application. Analysis is carried out to obtain the best alternative to accelerate the project. The results of this study can be carried out as much as 30% of project acceleration through the addition of 3 hours of overtime hours so that, from the beginning the target was completed in 34 days after acceleration, it became 25 days. Article in Journal/Newspaper Orca Jurnal Politeknik Pratama
institution Open Polar
collection Jurnal Politeknik Pratama
op_collection_id ftlppmpolprapurw
language English
topic Alternative Acceleration
Repair
Correlation
SPSS
spellingShingle Alternative Acceleration
Repair
Correlation
SPSS
Anauta Lungiding A.R
Nely Handayani Kusuma Hadi
Analisis Alternatif Percepatan Projek Reparasi ORCA LAUT 7296 Mengguankan Metode Korelasi SPSS
topic_facet Alternative Acceleration
Repair
Correlation
SPSS
description Repair activities are one of the ship maintenance schedules. In the ORCA LAUT 7296 ship repair project, acceleration of project activities is carried out to save repair time. This is done so that the ship can operate immediately and the shipyard can receive a new ship project that you want to repair or build a new ship. ORCA LAUT 7296 has several jobs, especially on hull replating activities due to the ship having run aground and experiencing a leak. In this study, an analysis of project acceleration was carried out using the correlation method with the help of the SPSS application. Analysis is carried out to obtain the best alternative to accelerate the project. The results of this study can be carried out as much as 30% of project acceleration through the addition of 3 hours of overtime hours so that, from the beginning the target was completed in 34 days after acceleration, it became 25 days.
format Article in Journal/Newspaper
author Anauta Lungiding A.R
Nely Handayani Kusuma Hadi
author_facet Anauta Lungiding A.R
Nely Handayani Kusuma Hadi
author_sort Anauta Lungiding A.R
title Analisis Alternatif Percepatan Projek Reparasi ORCA LAUT 7296 Mengguankan Metode Korelasi SPSS
title_short Analisis Alternatif Percepatan Projek Reparasi ORCA LAUT 7296 Mengguankan Metode Korelasi SPSS
title_full Analisis Alternatif Percepatan Projek Reparasi ORCA LAUT 7296 Mengguankan Metode Korelasi SPSS
title_fullStr Analisis Alternatif Percepatan Projek Reparasi ORCA LAUT 7296 Mengguankan Metode Korelasi SPSS
title_full_unstemmed Analisis Alternatif Percepatan Projek Reparasi ORCA LAUT 7296 Mengguankan Metode Korelasi SPSS
title_sort analisis alternatif percepatan projek reparasi orca laut 7296 mengguankan metode korelasi spss
publisher Pusat Riset dan Inovasi Nasional
publishDate 2023
url https://ejurnal.politeknikpratama.ac.id/index.php/jupiman/article/view/1567
https://doi.org/10.55606/jupiman.v2i2.1567
genre Orca
genre_facet Orca
op_source Jurnal Publikasi Ilmu Manajemen; Vol. 2 No. 2 (2023): Juni : Jurnal Publikasi Ilmu Manajemen; 01-15
2963-766X
2963-8712
10.55606/jupiman.v2i2
op_relation https://ejurnal.politeknikpratama.ac.id/index.php/jupiman/article/view/1567/1553
https://ejurnal.politeknikpratama.ac.id/index.php/jupiman/article/view/1567
doi:10.55606/jupiman.v2i2.1567
op_rights Copyright (c) 2023 Jurnal Publikasi Ilmu Manajemen
op_doi https://doi.org/10.55606/jupiman.v2i2.156710.55606/jupiman.v2i2
_version_ 1802010016116375552