Beltzville Lake Lehigh River Basin, Pohopoco Creek, Pennsylvania. Condition Report. Dam, Outlet Works and Spillway Periodic Inspection Report Number 1, July 1970

The first periodical inspection of Beltzville Lake Dam, Pohopoco Creek, was undertaken by representatives of the Office of the Chief of Engineer, North Atlantic Division and the Philadelphia District. The overall condition of the dam was very good with no significant cracking on the outlet works and...

Full description

Bibliographic Details
Other Authors: ARMY ENGINEER DISTRICT PHILADELPHIA PA
Format: Text
Language:English
Published: 1971
Subjects:
Online Access:http://www.dtic.mil/docs/citations/ADA081940
http://oai.dtic.mil/oai/oai?&verb=getRecord&metadataPrefix=html&identifier=ADA081940
id ftdtic:ADA081940
record_format openpolar
spelling ftdtic:ADA081940 2023-05-15T17:32:17+02:00 Beltzville Lake Lehigh River Basin, Pohopoco Creek, Pennsylvania. Condition Report. Dam, Outlet Works and Spillway Periodic Inspection Report Number 1, July 1970 ARMY ENGINEER DISTRICT PHILADELPHIA PA 1971-02 text/html http://www.dtic.mil/docs/citations/ADA081940 http://oai.dtic.mil/oai/oai?&verb=getRecord&metadataPrefix=html&identifier=ADA081940 en eng http://www.dtic.mil/docs/citations/ADA081940 Approved for public release; distribution is unlimited. Document partially illegible. DTIC AND NTIS Civil Engineering *STRUCTURAL ANALYSIS *EARTH DAMS DEFORMATION CONCRETE DEFECTS(MATERIALS) CONSTRUCTION MEASURING INSTRUMENTS INSPECTION EMBANKMENTS PENNSYLVANIA WATER EROSION *BELTZVILLE DAM DAM INSPECTION SPILLWAYS Text 1971 ftdtic 2016-02-22T15:03:36Z The first periodical inspection of Beltzville Lake Dam, Pohopoco Creek, was undertaken by representatives of the Office of the Chief of Engineer, North Atlantic Division and the Philadelphia District. The overall condition of the dam was very good with no significant cracking on the outlet works and no structural effects observed on the spillways although some of the weepholes in the spillway stabs were clogged with debris and required cleaning. Bridge movement was not observed and piezometers showed only minute and insignificant pressures. The inspection disclosed no serious problems but several minor deficiencies were noted in the embankment, particularly at contact with the abutments in the conduit and spillway. Repair measures were outlined to be undertaken to correct these deficiencies. Text North Atlantic Defense Technical Information Center: DTIC Technical Reports database
institution Open Polar
collection Defense Technical Information Center: DTIC Technical Reports database
op_collection_id ftdtic
language English
topic Civil Engineering
*STRUCTURAL ANALYSIS
*EARTH DAMS
DEFORMATION
CONCRETE
DEFECTS(MATERIALS)
CONSTRUCTION
MEASURING INSTRUMENTS
INSPECTION
EMBANKMENTS
PENNSYLVANIA
WATER EROSION
*BELTZVILLE DAM
DAM INSPECTION
SPILLWAYS
spellingShingle Civil Engineering
*STRUCTURAL ANALYSIS
*EARTH DAMS
DEFORMATION
CONCRETE
DEFECTS(MATERIALS)
CONSTRUCTION
MEASURING INSTRUMENTS
INSPECTION
EMBANKMENTS
PENNSYLVANIA
WATER EROSION
*BELTZVILLE DAM
DAM INSPECTION
SPILLWAYS
Beltzville Lake Lehigh River Basin, Pohopoco Creek, Pennsylvania. Condition Report. Dam, Outlet Works and Spillway Periodic Inspection Report Number 1, July 1970
topic_facet Civil Engineering
*STRUCTURAL ANALYSIS
*EARTH DAMS
DEFORMATION
CONCRETE
DEFECTS(MATERIALS)
CONSTRUCTION
MEASURING INSTRUMENTS
INSPECTION
EMBANKMENTS
PENNSYLVANIA
WATER EROSION
*BELTZVILLE DAM
DAM INSPECTION
SPILLWAYS
description The first periodical inspection of Beltzville Lake Dam, Pohopoco Creek, was undertaken by representatives of the Office of the Chief of Engineer, North Atlantic Division and the Philadelphia District. The overall condition of the dam was very good with no significant cracking on the outlet works and no structural effects observed on the spillways although some of the weepholes in the spillway stabs were clogged with debris and required cleaning. Bridge movement was not observed and piezometers showed only minute and insignificant pressures. The inspection disclosed no serious problems but several minor deficiencies were noted in the embankment, particularly at contact with the abutments in the conduit and spillway. Repair measures were outlined to be undertaken to correct these deficiencies.
author2 ARMY ENGINEER DISTRICT PHILADELPHIA PA
format Text
title Beltzville Lake Lehigh River Basin, Pohopoco Creek, Pennsylvania. Condition Report. Dam, Outlet Works and Spillway Periodic Inspection Report Number 1, July 1970
title_short Beltzville Lake Lehigh River Basin, Pohopoco Creek, Pennsylvania. Condition Report. Dam, Outlet Works and Spillway Periodic Inspection Report Number 1, July 1970
title_full Beltzville Lake Lehigh River Basin, Pohopoco Creek, Pennsylvania. Condition Report. Dam, Outlet Works and Spillway Periodic Inspection Report Number 1, July 1970
title_fullStr Beltzville Lake Lehigh River Basin, Pohopoco Creek, Pennsylvania. Condition Report. Dam, Outlet Works and Spillway Periodic Inspection Report Number 1, July 1970
title_full_unstemmed Beltzville Lake Lehigh River Basin, Pohopoco Creek, Pennsylvania. Condition Report. Dam, Outlet Works and Spillway Periodic Inspection Report Number 1, July 1970
title_sort beltzville lake lehigh river basin, pohopoco creek, pennsylvania. condition report. dam, outlet works and spillway periodic inspection report number 1, july 1970
publishDate 1971
url http://www.dtic.mil/docs/citations/ADA081940
http://oai.dtic.mil/oai/oai?&verb=getRecord&metadataPrefix=html&identifier=ADA081940
genre North Atlantic
genre_facet North Atlantic
op_source DTIC AND NTIS
op_relation http://www.dtic.mil/docs/citations/ADA081940
op_rights Approved for public release; distribution is unlimited. Document partially illegible.
_version_ 1766130317151698944