PRODUCTION ANALYSIS OF CUT-AND-COVER TRENCH CONSTRUCTION
During the 1961 and 1962 summer test seasons at Camp Century, Greenland, a 1600-ft-long trench containing horizontal curves was constructed. A total of 105 hr 45 min of Peter-plow machine time was required for the cutting operation. The overall cutting production, including spoil cuts, was 466 cu yd...