CONSTRUCTION DEWATERING AT SALUDA DAM; DESIGN, TESTING, AND IMPLEMENTATION

ABSTRACT The proposed Remediation of Saluda Dam, located approximately ten miles to the west of Columbia South Carolina and owned and operated by South Carolina Electric & Gas Company (SCE&G), consists of a 5,500-foot-long Rock Fill Berm and a 2,200-foot-long Roller Compacted Concrete (RCC)...

Full description

Bibliographic Details
Main Authors: John P Osterle, Paul C Rizzo, P E, William Argentieri, Jeffrey D Holchin
Other Authors: The Pennsylvania State University CiteSeerX Archives
Format: Text
Language:English
Subjects:
Online Access:http://citeseerx.ist.psu.edu/viewdoc/summary?doi=10.1.1.1061.3867
http://www.rizzoassoc.com/cms/images/stories/site/published_papers/construction_dewatering_saluda.doc.pdf
id ftciteseerx:oai:CiteSeerX.psu:10.1.1.1061.3867
record_format openpolar
spelling ftciteseerx:oai:CiteSeerX.psu:10.1.1.1061.3867 2023-05-15T17:08:23+02:00 CONSTRUCTION DEWATERING AT SALUDA DAM; DESIGN, TESTING, AND IMPLEMENTATION John P Osterle Paul C Rizzo P E William Argentieri Jeffrey D Holchin The Pennsylvania State University CiteSeerX Archives application/pdf http://citeseerx.ist.psu.edu/viewdoc/summary?doi=10.1.1.1061.3867 http://www.rizzoassoc.com/cms/images/stories/site/published_papers/construction_dewatering_saluda.doc.pdf en eng http://citeseerx.ist.psu.edu/viewdoc/summary?doi=10.1.1.1061.3867 http://www.rizzoassoc.com/cms/images/stories/site/published_papers/construction_dewatering_saluda.doc.pdf Metadata may be used without restrictions as long as the oai identifier remains attached to it. http://www.rizzoassoc.com/cms/images/stories/site/published_papers/construction_dewatering_saluda.doc.pdf text ftciteseerx 2020-04-19T00:20:02Z ABSTRACT The proposed Remediation of Saluda Dam, located approximately ten miles to the west of Columbia South Carolina and owned and operated by South Carolina Electric & Gas Company (SCE&G), consists of a 5,500-foot-long Rock Fill Berm and a 2,200-foot-long Roller Compacted Concrete (RCC) Berm. This combination RCC and Rockfill Berm will be constructed along the downstream toe of the existing 200-foot-high earth embankment dam. Should the existing Dam fail during a seismic event, the combination Rockfill and RCC Berm will serve as a backup dam to prevent an uncontrolled release of Lake Murray. Extensive foundation excavations into the residual soil or to bedrock at the toe of the existing Dam are required to facilitate the construction of the RCC and Rockfill Berm. To maintain an adequate factor of safety against slope instability for the existing Dam during construction, the existing phreatic surface within the Dam needs to be lowered substantially by dewatering. Based on the hydrogeologic conditions at the site, Paul C. Rizzo Associates (RIZZO) determined that the dewatering system should consist primarily of deep wells and eductors. Numerous components of this system that have been installed are currently operating to lower the phreatic surface within the Dam and downstream foundation excavation. Engineering analyses consisting of analytical models and finite element analyses were utilized to estimate the approximate spacing and flow rate required for the deep wells and eductors. Early indications are that the dewatering system will be successful in dewatering the existing Dam so that the construction can proceed without delay. Text Long Rock Unknown Long Rock ENVELOPE(-61.198,-61.198,-62.689,-62.689) The Toe ENVELOPE(-59.167,-59.167,-62.333,-62.333)
institution Open Polar
collection Unknown
op_collection_id ftciteseerx
language English
description ABSTRACT The proposed Remediation of Saluda Dam, located approximately ten miles to the west of Columbia South Carolina and owned and operated by South Carolina Electric & Gas Company (SCE&G), consists of a 5,500-foot-long Rock Fill Berm and a 2,200-foot-long Roller Compacted Concrete (RCC) Berm. This combination RCC and Rockfill Berm will be constructed along the downstream toe of the existing 200-foot-high earth embankment dam. Should the existing Dam fail during a seismic event, the combination Rockfill and RCC Berm will serve as a backup dam to prevent an uncontrolled release of Lake Murray. Extensive foundation excavations into the residual soil or to bedrock at the toe of the existing Dam are required to facilitate the construction of the RCC and Rockfill Berm. To maintain an adequate factor of safety against slope instability for the existing Dam during construction, the existing phreatic surface within the Dam needs to be lowered substantially by dewatering. Based on the hydrogeologic conditions at the site, Paul C. Rizzo Associates (RIZZO) determined that the dewatering system should consist primarily of deep wells and eductors. Numerous components of this system that have been installed are currently operating to lower the phreatic surface within the Dam and downstream foundation excavation. Engineering analyses consisting of analytical models and finite element analyses were utilized to estimate the approximate spacing and flow rate required for the deep wells and eductors. Early indications are that the dewatering system will be successful in dewatering the existing Dam so that the construction can proceed without delay.
author2 The Pennsylvania State University CiteSeerX Archives
format Text
author John P Osterle
Paul C Rizzo
P E
William Argentieri
Jeffrey D Holchin
spellingShingle John P Osterle
Paul C Rizzo
P E
William Argentieri
Jeffrey D Holchin
CONSTRUCTION DEWATERING AT SALUDA DAM; DESIGN, TESTING, AND IMPLEMENTATION
author_facet John P Osterle
Paul C Rizzo
P E
William Argentieri
Jeffrey D Holchin
author_sort John P Osterle
title CONSTRUCTION DEWATERING AT SALUDA DAM; DESIGN, TESTING, AND IMPLEMENTATION
title_short CONSTRUCTION DEWATERING AT SALUDA DAM; DESIGN, TESTING, AND IMPLEMENTATION
title_full CONSTRUCTION DEWATERING AT SALUDA DAM; DESIGN, TESTING, AND IMPLEMENTATION
title_fullStr CONSTRUCTION DEWATERING AT SALUDA DAM; DESIGN, TESTING, AND IMPLEMENTATION
title_full_unstemmed CONSTRUCTION DEWATERING AT SALUDA DAM; DESIGN, TESTING, AND IMPLEMENTATION
title_sort construction dewatering at saluda dam; design, testing, and implementation
url http://citeseerx.ist.psu.edu/viewdoc/summary?doi=10.1.1.1061.3867
http://www.rizzoassoc.com/cms/images/stories/site/published_papers/construction_dewatering_saluda.doc.pdf
long_lat ENVELOPE(-61.198,-61.198,-62.689,-62.689)
ENVELOPE(-59.167,-59.167,-62.333,-62.333)
geographic Long Rock
The Toe
geographic_facet Long Rock
The Toe
genre Long Rock
genre_facet Long Rock
op_source http://www.rizzoassoc.com/cms/images/stories/site/published_papers/construction_dewatering_saluda.doc.pdf
op_relation http://citeseerx.ist.psu.edu/viewdoc/summary?doi=10.1.1.1061.3867
http://www.rizzoassoc.com/cms/images/stories/site/published_papers/construction_dewatering_saluda.doc.pdf
op_rights Metadata may be used without restrictions as long as the oai identifier remains attached to it.
_version_ 1766064118721150976